In short
Yes, once it has asked in writing. The local planning authority, the council that decides planning applications for the area, must then tell the parish council about applications for land in the parish, and about changes to them that it accepts. The parish council has 21 days from being told to send its comments: 18 days for some hospital, school, college, university and prison projects, and 14 days for an application for permission in principle. It must also tell the authority "as soon as practicable" whether it intends to comment. The authority must not decide the application before that period is over, unless the parish council has already sent its comments or said it will not make any. Where a neighbourhood plan covers all or part of the parish, the council may be told without asking, on the conditions set out below.
Applies to: Parish and town councils in England. A town council is the council of a parish that has taken the status of a town (see section 245 of the Local Government Act 1972), so the same rules apply to it. The paragraph that gives the right names only the council of a parish, so it gives no right to a parish meeting in a parish with no council.
Asking to be told
The right to be told depends on a request. The request must:
- be in writing; and
- say that the council wants to be told of all relevant applications, or of all applications of a kind it describes, such as applications for new homes.
Neither the paragraph nor the Interpretation Act 1978, which says what "writing" includes in an Act, mentions email. To be safe, ask the authority to confirm that it has the council's request, and keep its reply.
A relevant application is one for land in the parish that asks for:
- planning permission;
- permission in principle; or
- approval of matters left to be settled after outline planning permission was granted, called "reserved matters" (see section 92 of the Town and Country Planning Act 1990). Under the 2015 order described below, these can be access, appearance, landscaping, layout and scale.
An application to carry out development without keeping to the conditions of an earlier planning permission is itself an application for planning permission (section 73), so it is included. The list does not include applications for a non-material change to a planning permission, or for a certificate of lawful use or development.
The duty to tell the parish council falls on each authority that decides planning applications. Outside a National Park, where there is both a county council and a district council, the district council decides most applications, and the county council decides those about a "county matter", such as mineral working (see paragraphs 1 and 3 of Schedule 1 to the 1990 Act). So write to each authority whose applications you want to hear about.
The paragraph that gives the right sets no end date for a request. If you are not sure whether your council has ever made one, ask the planning authority, or send a new one.
Example of a request
The parish council asks to be notified of all relevant planning applications for land in the parish, under paragraph 8 of Schedule 1 to the Town and Country Planning Act 1990.
A council that wants only some kinds of application describes them in its request instead.
How the authority tells you
The authority can either send the council a copy of the application, or tell it in writing what is proposed and which land it is on. The paragraph does not mention lists, but it follows that a written list which describes each proposal and identifies its site would meet it.
It must also tell the council of any change to the application that it accepts, by sending a copy of the change or telling the council in writing of its general effect. It need not do so for a change that in its opinion is trivial.
The paragraph sets no time by which the authority must tell the council.
Without asking: where there is a neighbourhood plan
A parish council is told about applications without having to ask if:
- a neighbourhood area, an area designated for a neighbourhood plan, takes in all or part of its parish; and
- that area has a neighbourhood plan that has been made, or approved at a referendum; or a draft plan that has passed its examination, until it is made or turned down.
The applications it is told about are those for land in the neighbourhood area, of the same three kinds as above. If the neighbourhood area also takes in all or part of another parish, this applies only if the other parish council has agreed to your council acting for that area (see section 61F of the 1990 Act). The exact stages at which a draft plan counts are in section 70(3B) to (3F) of that Act.
The council can opt out of this, or ask to be told only of applications of a kind it describes, by telling the authority in writing.
How long the council has to respond
These rules come from an order made in 2015, linked in the Source list below. Applications for permission in principle have their own rules, further down.
Once it has been told of an application, the parish council must:
- tell the authority "as soon as practicable" whether it intends to comment; and
- send any comments within 21 days of being told of the application.
The shorter period. The 21 days become 18 days for an application for planning permission for what the order calls "public service infrastructure development". This is a project whose main purpose is to build, extend or alter an NHS hospital, a school or college of a kind the order lists, a university or other higher education institution, or a prison or a place where young people are held in custody, and which is "major development". Major development includes a project that creates 1,000 square metres or more of floor space, or is carried out on a site of a hectare or more. It does not include a project that needs an environmental impact assessment. The full definitions are in article 2 of the 2015 order. If an application is for one of these kinds of building and you cannot tell whether the shorter period applies, work to 18 days.
Counting the days. The article that sets the 21 days does not say whether they run from the day the notice was sent or the day it arrived, or whether that day counts. It does not leave out weekends or bank holidays. The safe course is to count from the date on the notice, as the first day, to count every day, and to make sure the comments reach the authority by the last day. For a notice dated 3 March, that means comments must reach the authority by 23 March.
The order also says that a document the order requires to be sent, if sent electronically and received outside the recipient's business hours, counts as received on the next working day. It does not say in so many words whether that covers the council's comments, so send comments during the authority's working hours.
When the authority may decide. The authority must not decide the application until the first of these happens:
- the parish council tells it that it will not comment;
- the parish council sends its comments; or
- the 21 days (or 18) are over.
So, as far as these rules go, once the parish council has sent comments the authority may decide straight away, even if the 21 days are not over. Send the council's full comments in one go. Telling the authority that the council intends to comment does not let it decide early: it must still wait until the comments arrive or the 21 days are over.
Comments sent late. When it decides, the authority must take into account "any representations received from the council of the parish". Those words are not limited to comments received within the 21 days. But the authority may decide as soon as the 21 days are over, so comments sent late may arrive after the decision.
Changes to an application. The article that sets the 21 days counts them from being told of the application, and does not say whether being told of a change starts a fresh 21 days.
Between meetings. The 21 days may end before the council next meets. A council can arrange for a committee, a sub-committee or the clerk to deal with planning comments: see What can a parish or community council delegate to a committee, a sub-committee or its clerk? Whether a vote by email can decide the council's comments is on Can a parish or community council take a decision between meetings, by email or otherwise, without delegating it?
The authority must take the parish council's comments into account when it decides the application. The rule requires it to take them into account, not to do what they ask.
The parish council must then be told the decision. If the application is referred to the Secretary of State, it must be told the date when it was referred, and later the Secretary of State's decision. Outside a National Park, where there is both a county council and a district council, the district council tells it the decision, even on an application the county council decided. In a National Park, the National Park authority tells it.
Applications for permission in principle
The same request covers applications for permission in principle. For these, the rules come from a separate order made in 2017, linked in the Source list. They are like the rules above, with a shorter period:
- the parish council must tell the authority "as soon as practicable" whether it intends to comment, and send any comments within 14 days of being told of the application;
- the authority must not decide the application until the parish council says it will not comment, sends its comments, or the 14 days are over, and must take into account any comments it receives; and
- the parish council must be told the decision or, if the application is referred to the Secretary of State, the date when it was referred and later the Secretary of State's decision.
The 2017 order's article on parish councils sets the 14 days for a council that is told because it asked, and does not say in so many words how long a council told because of a neighbourhood plan has. But its rule that the authority must wait is worded for any parish council that must be told, and ends when the 14 days are over. So a council told because of a neighbourhood plan should send any comments within 14 days too.
What this page does not cover
Sources
- Town and Country Planning Act 1990, Schedule 1, paragraph 8, on the right to be told, and paragraph 1 and paragraph 3, on which authority decides an application, read as revised
- Section 61F, on a parish council acting for a neighbourhood area; section 70, subsections (3B) to (3F), on when a draft neighbourhood plan has passed its examination; section 73, subsection (1), on applications to depart from conditions; and section 92, subsection (1), on reserved matters, of the same Act, read as revised
- Town and Country Planning (Development Management Procedure) (England) Order 2015, article 25, on the time to respond, when the authority may decide and telling the council the decision; article 2, on public service infrastructure development, reserved matters and documents sent electronically; and article 1, on the order applying to England only and not to permission in principle, all read as revised
- Town and Country Planning (Permission in Principle) Order 2017, article 5M, on the time to respond to an application for permission in principle, when the authority may decide it and telling the council the decision, read as revised
- Interpretation Act 1978, section 5 and Schedule 1, on what "writing" includes, read as revised
- Local Government Act 1972, section 245, on town councils, read as revised
The official website shows the 1990 Act and the 1972 Act as up to date to 14 or 15 November 2026. It lists changes not yet applied to both Acts, among them changes to sections 70, 73 and 92 of the 1990 Act, none of them to the subsections or words this page relies on, and none to the other provisions read for this page. It lists none not yet applied to the 2015 order, the 2017 order or the 1978 Act.
Last checked against the source on 15 November 2026.