How long does a parish council have to answer a freedom of information request?

England and Wales. Last checked against the source on .

Promptly, and at the latest on the 20th working day after the day the council receives the request. By then the council must tell the person in writing whether it holds the information and, if it does, send it to them, apart from any part the Freedom of Information Act 2000 lets it refuse. If it refuses any part, it must send the person a refusal notice by that 20th working day too. The notice has to say what the council relies on and how the person can complain, as set out below. In one narrow case, for some vexatious and repeated requests, no notice is needed. Saturdays, Sundays, Christmas Day, Good Friday and bank holidays in any part of the UK are not working days. In a few cases, also explained below, the council has longer.

Applies to: Every parish and town council and every parish meeting in England, and every community and town council in Wales. A town council is the council of a parish or community that has taken the status of a town, so it is covered in the same way. So is the council of a parish in England that has the style of community, neighbourhood or village.

What counts as a request

Anyone can make a request. It counts as a request under the Act if it:

Nothing in that list asks for a reason, a mention of the Act, or a particular person to send it to. A request sent electronically, such as by email, counts as in writing if it arrives in a form that can be read and can be kept to refer to later. The section that sets these rules does not say whether an email address is enough as the address for correspondence. It does not rule one out, so treating such a request as one under the Act is the safe course.

A request about the environment, such as about land or planning, may come under other rules: see the page on environmental requests.

The Act covers information recorded in any form, such as documents and emails. Information that someone else holds on the council's behalf counts as held by the council. Information the council holds only on someone else's behalf does not.

Counting the 20 working days

The day the council receives the request does not count. Day 1 is the next working day, and the council must answer on or before day 20. Section 10 does not say when an email that arrives out of hours, or on a day that is not a working day, counts as received. Counting from the day it reaches the council's inbox is the safe course, since that is the earliest it could count. The 20th working day is the latest day, not a target: the Act says "promptly".

A working day is any day except a Saturday, a Sunday, Christmas Day, Good Friday or a bank holiday "in any part of the United Kingdom". Those words include a day that is a bank holiday only in Scotland or only in Northern Ireland, so such a day is not a working day either, even for a council in England or Wales. For example, St Andrew's Day, 30 November, is a bank holiday in Scotland, or the Monday after it when it falls at a weekend. GOV.UK lists each year's bank holidays for each part of the UK.

Example. A request arrives by email on Monday 16 November 2026. Day 1 is Tuesday 17 November. Monday 30 November 2026 is St Andrew's Day, so it is not counted. Day 20, the last day to answer, is Tuesday 15 December 2026.

When the council has longer

It needs more detail to find the information. Sometimes the council reasonably needs further information to identify and find what is being asked for. Once it has told the person so, it does not have to answer until it gets that information, and the 20 working days then run from the day it arrives. These rules set no time limit for asking.

It asks for a fee. The council may send the person a written fees notice, within the 20 working days, saying what it will charge. It then need not answer unless the fee is paid within three months, counting the day the notice is given as the first day. If the fee is paid in that time, the count of working days stops: the days from the day the notice is given to the day the fee arrives, both included, are not counted. Unless another law sets the fee, it can cover only the cost of telling the person whether the council holds the information and of sending it, such as copying and postage, and not the time that staff or anyone else spends on it for the council.

The public interest has to be weighed. Some exemptions in the Act apply only if the public interest in withholding the information outweighs the public interest in releasing it. Where information falls under one of these, the council need not answer that part of the request until a time that is reasonable in the circumstances. The section that allows this does not say how long that is. The rest of the request must still be answered within the 20 working days, and the refusal notice must still be sent by then. It must say which exemption the council relies on. If the council has not yet decided where the public interest lies, the notice must also state that it has not decided, and give its estimate of the date by which it expects to have decided.

Two rare cases. The council can apply for more time to the Information Commission, which took over from the Information Commissioner on 30 September 2026, if it cannot answer within the 20 working days because:

It must apply within the 20 working days. The Commission then sets a later day that it considers reasonable, no later than the 60th working day, counted in the same way as the 20. The rules are in regulations 5 and 6 of the Freedom of Information (Time for Compliance with Request) Regulations 2004.

Answering the request

The answer covers the information the council held when it received the request. The council may take account of a change or deletion made since then, but only one that would have been made even if the request had not come.

If, when asking, the person said they would like a copy, a chance to inspect a record, or a summary of the information, the council must do as they asked so far as reasonably practicable. In deciding what is reasonably practicable, it may take all the circumstances into account, including the cost. If it cannot do as they asked, it must tell them why. Otherwise it may send the information in any way that is reasonable in the circumstances. If, when asking, the person said they would like an electronic copy of information in a "dataset", the council must, so far as reasonably practicable, give it in an electronic form that can be re-used. Section 11 of the Act defines a dataset: broadly, a collection of facts that the council gathered for its work and keeps electronically, much as they were recorded.

The council must give people who plan to make a request, or have made one, the advice and help that it would be reasonable to expect of it. A council that follows what the government's code of practice under section 45 says about advice and help is treated as having met this duty.

Refusing, and the refusal notice

Within the 20 working days, the council must send a refusal notice if, for any part of the request, it relies on:

The notice must:

A separate notice of reasons must carry those last two details too. The council need not say why an exemption applies, or give its reasons on the public interest, if doing so would itself reveal exempt information.

The exception for vexatious and repeated requests. The council need not send a notice saying it relies on the rule against vexatious or repeated requests if it has already sent that person such a notice about an earlier request, and it would be unreasonable in all the circumstances to expect it to send another.

The cost limit: if answering would cost too much

The council need not send the information if it estimates that answering the request would cost more than £450. It must still tell the person whether it holds the information, unless that alone would cost more than £450. The £450 limit applies to every parish, town and community council and parish meeting.

In its estimate the council may count only what it reasonably expects to spend on:

The time that anyone is expected to spend on those tasks for the council, staff or not, counts at £25 an hour for each person. So £450 is 18 hours of work, where time is the only cost.

Two or more requests can be added together where:

The cost of answering any one of them is then taken to be the cost of answering them all.

If the council misses the time

A person who thinks the council has not dealt with their request as the Act requires, for example by answering late, can apply to the Information Commission for a decision. The Commission need not decide if, among other reasons, the person has not first completed any complaints procedure that the council provides in line with the code of practice, or has waited too long to apply.

What this page does not cover

Source

All read as revised, unless marked as made.

The official website shows no outstanding changes for the sections of the 2000 Act, its Schedule 1, the fees regulations or the 1971 Act. It shows the sections of the 1972 Act as up to date, with changes not yet made only to other provisions. It holds the time regulations, and the two sets of 2026 regulations, only as made.

Last checked against the source on 14 November 2026.